Scope 20: El Dorado, MO Site Survey Completion

Scope 20: El Dorado, MO Site Survey Completion#

  • Scope ID: 20

  • Owner: Kyle Winans

  • Duration: 24 Hours

  • Date: 10/8/2024

  • Due: 10/13/2024

  • Actual Completion Date: 10/20/2024

Overview#

In strict adherance to scope 13 or having adapted the deliverables from scope 13, ensure the second site survey adheres to a current product description to be marketted by the end of October 2024.

Justification#

Complete the second site survey to get paid. Complete the site survey product to continue getting paid.

Deliverables#

  1. Site survey repository within the R2 bucket

  2. Complete manifest file

  3. Run site survey utility.

  4. Print all covers

  5. Print all sets

  6. Hole punch and install all sets

  7. Travel to site

  8. Install all documents

  9. Send all deliverables per product description

  10. Charlie send final billing for payment